Project Cargo and Out-of-Gauge Shipping: What Changes

8 min read
Share:
Project Cargo and Out-of-Gauge Shipping: What Changes

Frequently Asked Questions

What is the difference between out-of-gauge and breakbulk?+

Out-of-gauge cargo still travels on container equipment such as a flat rack or open top, but overhangs it in height, width or length. Breakbulk is too large or heavy for any container equipment and is loaded loose into the hold of a multipurpose vessel. Heavy lift goes further still, exceeding normal crane capacity and requiring specialist vessel gear. Each step changes the vessel, the ports that can handle it, and the price substantially.

Why is out-of-gauge freight so expensive?+

Because you pay for space you do not fill. Cargo overhanging a flat rack sterilises the container slots beside and above it, and those blocked empty slots are often the single largest line in the quote. On top of that sit lifting arrangements at both ends, engineered lashing and securing, route surveys, road permits and sometimes escorts. This is why an out-of-gauge quote takes days rather than minutes.

What information does a forwarder need to quote project cargo?+

Per piece: exact dimensions in the shipping condition including any cradle or frame, actual rather than estimated weight, the marked centre of gravity and lifting points, whether the piece can be tilted, laid down or dismantled, drawings or dimensioned photographs, and the access constraints at both the collection and delivery sites. Vague dimensions are the main cause of quotes that change later.